Major sbX Progress Seen on E Street

Landscaping has been put in at the Marshall Blvd. park-and-ride lot.

March has been a very busy month for construction crews working on the Omnitrans sbX Bus Rapid Transit Line Construction Project. All throughout the project corridor, construction progress can be seen – especially along E Street from Marshall Boulevard to Hospitality Lane.

On the north end of E Street, a variety of drought-resistant trees, including willows and shrubs, are being planted at the west and east lots of the Marshall Boulevard park-and-ride. At Highland Avenue, the steel structure for the side-boarding sbX station has been installed on the west side of the street.

In the downtown area between 6th and 2nd streets, work on the west side of E Street has focused on relocation of fire hydrants, storm drains, and sidewalk ramps. A section of sidewalk also was completed at Court Street. Current activities at the Rialto Avenue and North Mall Way stations have crews working on building planter walls.

E Street center-running lanes

Finally, a big milestone on the south end of E Street was the completion of asphalt work in the center running lanes between Orange Show Road and Hospitality Lane. Crews reinforced the roadway by removing the old asphalt, putting in a subgrade, base, geogrid mesh, and the new asphalt.

 – Robert Chevez
   rchevez@westboundcommunications.com

Visit Omnitrans sbX on Facebook
http://facebook.com/omnitrans.sbx


Do you like this story and want to use it for your blog or newsletter? All our stories may be freely re-posted and shared with others!

Leave a Reply

Your email address will not be published. Required fields are marked *