Roadway, Station Work Progress on Hospitality

The T-intersection on Hospitality Lane and the main entrance to Home Depot was reopened to traffic after interim center-running-lane work was completed.

In August, crews completed placing various layers of road reinforcement in the sbX center-running lane areas on the portion of Hospitality Lane east of Waterman Avenue. The T-intersection at the main entrance to Home Depot also was reopened.

Concrete curbs, gutters and sidewalks were poured between Carnegie Drive West and Carnegie Drive East. Additionally, concrete pavers were installed at the Hospitality Lane sbX stations at Tippecanoe Avenue, Carnegie Drive and Hunts Lane.

Throughout September, there will be extensive masonry work as well as electrical activities to ultimately wire the stations for lighting, LED variable message signs, electronic ticket-vending machines and security cameras.

-Kelly Koehler

 

Do you like this story and want to use it for your blog or newsletter? All our stories may be freely re-posted and shared with others!

Visit Omnitrans sbX on Facebook
http://facebook.com/omnitrans.sbx

Omnitrans Ops Develops sbX Plan

The sbX station and park & ride testing at Palm & Kendall in San Bernardino. The station will service both Omnitrans sbX and fixed route vehicles.

The Omnitrans operations department is gearing up for the 2014 opening of sbX bus rapid transit (BRT) service. It will be “all hands on deck” in developing standards, operating requirements, procedures, policies, and training skills to support this premier service!

The plan will familiarize department personnel with preemptive signal priority, dedicated center running bus lanes, bus arrival prediction and messaging system, on board passenger wireless network service, ticket vending machines, and on-board/ platform surveillance for increased security, and vehicle operations.

It is anticipated that six months prior to the system being in revenue service, vehicles will be traveling the sbX corridor for operators to test equipment functionality, headways, and approaches at the platform stations.

The first transit station to be evaluated for maneuverability and stall placement was at Palm & Kendall. The best way to test whether or not the transit station is “sbX ready” is to create an environment as close to reality as the coach operators will experience.

Although you might imagine the 60-foot articulated buses require a wider turning radius than the 40-foot buses, that is not the case. Details are crucial; measurements are tested and retested to ensure there are no barriers to the safe operation of the buses.

It is anticipated the sbX service will require 23 coach operators to operate the system five days a week. We are in the beginning stages of planning tight now and will continue to post more details as we move closer to our implementation date.

More testing at the Kendall and Palm Park and Ride

Do you like this story and want to use it for your blog or newsletter? All our stories may be freely re-posted and shared with others!

Do you have a great Omnitrans story to share? Let us know!

Email Juno Kughler Carlson at  juno.carlson@omnitrans.org